Keralam: Parts of Punjab went without electricity for around 14 hours a day this year. Yet in the last financial year, India exported nearly twice as much power as it imported. It is normal for nations to share energy. The question is how much.
As per the official records of the Central Electricity Authority (CEA), India imported 11,188 MU (million units) while it exported 21,067 MU, making the net export 9,879 MU during the financial year 2025–2026.
According to the CEA's Annual Reports for 2025–26, India exported electricity to countries like Bangladesh, Bhutan, Nepal and Myanmar. The electricity export to Bangladesh includes both Indian-grid exports and supply from Adani Power's Godda plant, which is not connected to the Indian grid.
Now, several states inside the country are suffering power shortages. Several of them have faced supply pressures and invited short-term tenders to acquire additional electricity. This again makes one think about how India can continue with electricity exports while some of its own states struggle to meet demand.
Nonetheless, the given figures don't necessarily imply that electricity exports happened at the cost of sacrificing domestic demand. Electricity trade depends on various factors such as the availability of power generation options, demand, transmission capacity and specific supply arrangements.
In 2026, several Indian states reported power shortages, specifically during peak hours. Punjab's shortages were severe enough that the Union Government eventually arranged additional power for the state.
Gujarat also demanded that its production units reduce power intake during evening peak hours after demand rose and coal stocks at various power units ran low.
As per the reports of The Indian Express, several Indian states such as Gujarat, Rajasthan, Maharashtra, Madhya Pradesh, Tamil Nadu and Keralam sought additional power for November and December through short-term tenders.
Despite this, several states couldn't secure the sought-after units of power but had to be satisfied with whatever they got. Tamil Nadu, for example, floated a tender for 1,000 MW for November but was only given 377 MW. Rajasthan asked for 1,500 MW but had to settle for 85 MW. Maharashtra, however, could not procure any power against its 500 MW tender. Keralam asked for around 1,800 MW for November but had to compromise with 270 MW. Keralam asked for 2,100 MW for December; however, it got only 655 MW.
Weaker hydropower generation is a major cause of electricity shortages across the states. Officials told Reuters that weaker hydropower had "tightened supplies available for redistribution". The Union Government usually has 14 to 15 gigawatts of coal and hydropower it can allocate to states during a shortfall. Hydropower generation was down 20 per cent from a year earlier, according to government data cited by Reuters.
Another major hurdle for electricity availability was maintenance work at power plants and declining coal inventories. Adding to this, another important challenge was the difference between daytime and evening power demands. Even though solar power production contributes efficiently to power demand during daytime, demand still remains high after sunset. Without enough battery storage to hold daytime solar power for use after sunset, meeting daily demand will remain the biggest challenge.
So, exporting electricity doesn't necessarily mean that India is self-sufficient in all terms. India's current power generation structure shows the country's ability to produce and supply electricity under specific conditions and structured arrangements. This doesn't mean that every state is capable of ensuring sufficient power during all hours.
The country runs on an interconnected power grid, but electricity availability heavily depends on the location of power generation, the feasibility of transmission networks and demand at a fixed time. This implies that the surplus from one region may not necessarily solve peak-hour demand or another region's power shortage.
India should now focus on two aspects: cross-border electricity coordination and overcoming hurdles to ensure reliable domestic supply. The country needs to bridge the gap between the surplus amount of electricity being produced and finding sustainable ways to ensure that power reaches consumers when they demand it.